I-80 Gold has begun production mining at its Archimedes underground project on schedule, marking first gold mined from the Nevada asset and the company’s second underground mine to come online.
The company said it has started mining both oxide and sulfide material. Oxide ore is now being placed on the active heap leach pad at Ruby Hill, while sulfide material is being stockpiled for processing at Lone Tree next year.
Archimedes has about 3,600 meters of lateral development completed so far, and the underground contractor is said to be exceeding planned productivity rates in the upper 426 zone. The company said production mining began after completion of the surface and underground infrastructure needed to start operations, including ventilation and escape raises.
Construction on Archimedes began in September 2025. The company said the project has tracked largely in line with the March 2025 preliminary economic assessment, except for expanded and upgraded surface infrastructure to support larger future operations. With that added infrastructure, total project capital is now expected to be about $10 million higher than the $47.3 million estimate in the PEA.
The company said the focus now shifts to ramping up mining through 2027 and stockpiling refractory material ahead of Lone Tree’s planned commissioning late next year. I-80 Gold is targeting consolidated annual gold production of 150,000 to 200,000 ounces starting in 2028 from Archimedes and Granite Creek underground.
At Archimedes, the company said the mix of material mined in 2027 is expected to be mostly oxide, not sulfide. That is a change from the PEA, which assumed more sulfide material would be toll milled at a 58% payability factor. Because of the stronger oxide mix, I-80 Gold said it expects to increase its heap leach production outlook, with full guidance due early next year.
The company also said oxide material mined from the upper 426 zone began going onto the heap leach pad in mid-November, with first gold recovery from that material expected in the first quarter of 2027.
On the processing side, I-80 Gold said all refractory material mined at Archimedes in 2027 is expected to be stockpiled, along with a large portion of refractory material from Granite Creek underground, rather than sent to a third-party facility. Those stockpiles are intended for processing at Lone Tree after the plant’s planned commissioning in the fourth quarter of 2027.
Drilling activity is continuing at Archimedes. Seven underground drill rigs are active, with about 55,000 meters planned across 140 drill holes. The drilling campaign is expected to run through the second quarter of 2027 and is aimed at evaluating extensions and improving resource definition for a feasibility study planned for the second half of 2027.
As of December 31, 2025, Archimedes contained an indicated resource of 1.8 million tonnes grading 7.6 grams per tonne for 436,000 ounces of gold, plus an inferred resource of 4.2 million tonnes grading 7.3 grams per tonne for 988,000 ounces. Today the company's shares have moved 0.93% to a price of $1.09. For more information, read the company's full 8-K submission here.